Brettenwood Lakes Update
The sales are substantially concluded at Brettenwood Lakes and the construction on the first 2 blocks (of the 2 bedroom units) is well under way.

We have redesigned one of the 1 bedroom blocks to a 2 bedroom block in response to popular demand and we will launch the details of this shortly for sales.

With a construction schedule of between 14 and 16 months, we look forward to completing this development during the 4th quarter of 2016.

Pelican Place Update
The planned storage facility at Pelican Place has been submitted for final council approval and once we have received the final go ahead works will commence in earnest. The two units known as Pelican Perch opposite Heron dam will be included in this project as two number, double storey three bedroom units.

Wagtail Update
We are looking to launch this project during the 2nd quarter of 2016. This project will certainly be a jewel in the crown with incredible sea views from every unit and all within a wonderful forest ambiance which is to be respected and appreciated.

Retirement Community Update
Forest Village Phase 2
The Forest Village Phase 2 project is nearing final completion with the transfer of 9 of the last 13 units imminent which will leave the last 4 units to be completed and handed over which is on schedule for September 2015.

Forest Village Phase 3
We now have approximately 21 out of 35 units sold in this Phase. The first 3 units (33, 34 & 35) are a few weeks away from final completion. After some initial delays we are now expecting to have the Sectional title register open by end August 2015.

Forest Village Phase 4
This area is zoned for 33 units and planning will commence shortly on the Design Development and approvals stage. This is the final Phase of the Forest Village Project and we hope that this Phase will incorporate all the lessons learned on resident needs and requirements making it the most sought after Phase within the Village.